Today was the last full day of construction for the house. The PV, battery and inverter system has been inspected and approved. All the light fixtures and fans are in. The Apricu solar hot water system was installed today. We had 100 degree water after only four hours.
Things that will be worked on tonight and tomorrow:
Finish painting
Trim on the curved header
Landscaping
Furniture will be delivered
UMR was the first team to have the decks setup and ready for the event deck walk way to be installed.
Last night there was a bit of rain in D.C. Good news for us! The house doesn’t leak! Luckily it has cooled off a bit since then.